PMP-PPL: People

People domain: common vision, conflict management, team leadership, stakeholder engagement, knowledge transfer, and communication - 33% of the July 2026 PMP exam.

PMP exam domain

What you will learn in PMP-PPL

  • Develop a common vision
  • Manage conflicts
  • Lead the project team
  • Engage stakeholders
  • Align stakeholder expectations
  • Manage stakeholder expectations
  • Help ensure knowledge transfer
  • Plan and manage communication

Free PMP-PPL study-note previews

Free PMP-PPL practice questions

A sample of 5 questions from the PMP-PPL question bank, with the answer and explanation for each. Try answering before you open the answer.

  1. Question 1

    Which form of power is MOST effective for a project manager working in a matrix organization where team members report to functional managers?

    • ALegitimate power - using the PM's formal position and title
    • BCoercive power - using consequences for non-compliance
    • CExpert power - demonstrating knowledge and competence that the team respects
    • DReward power - providing bonuses and promotions for good performance
    Show answer and explanation

    Correct answer: C - Expert power - demonstrating knowledge and competence that the team respects

    Expert power is the most effective form of power for PMs, especially in matrix organizations where formal authority is limited. When team members respect the PM's knowledge and competence, they follow voluntarily. PMI emphasizes expert and referent power as the most sustainable forms of influence for project managers.

    Why the other options are wrong

    • A: In a matrix organization, the PM's formal authority over team members is limited. Functional managers have more legitimate power over their reports.
    • B: Coercive power damages trust and is the least effective form of power. PMI strongly advises against it.
    • D: In most matrix organizations, the PM does not control compensation or promotion decisions. This power resides with functional managers.
  2. Question 2

    A project requires the team to use a new cloud platform that none of the members have experience with. When should the project manager plan for training?

    • ADuring the execution phase when the team first encounters the platform, scheduling ad hoc training sessions to address problems as they arise and minimise disruption to early sprint work
    • BDuring the planning phase, scheduled before the team needs to use the technology
    • CAfter the project begins if team members struggle with the platform
    • DTraining falls outside the PM's direct authority - team members and their functional managers are responsible for identifying and arranging their own technical skill development
    Show answer and explanation

    Correct answer: B - During the planning phase, scheduled before the team needs to use the technology

    Training should be planned during the planning phase and delivered before the team needs the skill. This is part of resource management planning and the training needs assessment. Budget and schedule should account for training time. Proactive training prevents delays, rework, and frustration during execution.

    Why the other options are wrong

    • A: Training during execution causes delays because the team cannot be productive while learning. Training should precede the need.
    • C: Reactive training leads to rework, delays, and frustration. Proactive planning identifies training needs early.
    • D: While self-study is valuable, the PM is responsible for ensuring the team has adequate skills. Training needs should be identified and planned as part of resource management.
  3. Question 3

    A newly formed agile team asks the project manager to assign tasks to each team member for the upcoming sprint. How should a servant leader respond?

    • AAssign tasks by matching each team member's documented skills and experience to sprint backlog items, then monitor adherence and adjust assignments throughout the sprint
    • BCoach the team on self-organization and help them learn to select their own work
    • CAsk the Scrum Master to assign the tasks instead
    • DCreate a RACI matrix to clarify task ownership
    Show answer and explanation

    Correct answer: B - Coach the team on self-organization and help them learn to select their own work

    Servant leadership means empowering the team rather than directing them. In agile, teams self-organize - they decide who works on what. The PM's role is to coach and support the team in developing this capability, especially with newly formed teams. Over time, the team builds confidence in managing their own work distribution.

    Why the other options are wrong

    • A: A servant leader does not assign tasks. Agile teams self-organize and pull work based on their capacity and skills.
    • C: Neither the PM nor the Scrum Master assigns tasks in agile. Both should support team self-management.
    • D: While RACI is useful in predictive projects, it contradicts agile self-organization principles. The team should choose their own work.
  4. Question 4

    A project team has just been assembled. Team members are polite but cautious, avoiding conflict and waiting for direction from the project manager. According to the Tuckman model, which stage is the team in?

    • AStorming
    • BForming
    • CNorming
    • DPerforming
    Show answer and explanation

    Correct answer: B - Forming

    In the forming stage of the Tuckman model, team members are getting to know each other. They tend to be polite, avoid conflict, and look to the leader for direction and guidance. The PM should provide clear structure, define roles, and create opportunities for team members to build relationships during this stage.

    Why the other options are wrong

    • A: Storming involves open conflict and challenges. This team is avoiding conflict, which is characteristic of forming.
    • C: Norming involves established trust and working agreements. This team hasn't yet built those relationships.
    • D: Performing teams are highly autonomous and efficient. This team is still looking to the PM for direction.
  5. Question 5

    Which document BEST helps a project manager identify the types and quantities of resources needed for a project?

    • AThe project charter
    • BThe resource management plan
    • CThe stakeholder register
    • DThe risk register
    Show answer and explanation

    Correct answer: B - The resource management plan

    The resource management plan identifies how resources will be acquired, allocated, managed, and released. It specifies the types of resources (roles, skills), quantities needed, and timing of resource requirements. This plan is part of the overall project management plan and guides the PM in acquiring the right resources at the right time to execute the project successfully.

    Why the other options are wrong

    • A: The project charter authorizes the project but typically doesn't detail specific resource requirements.
    • C: The stakeholder register identifies stakeholders, not project resource requirements.
    • D: The risk register tracks project risks, not resource needs.

Practise these interactively

Study PMP-PPL on Examova

Frequently asked questions

What does PMP-PPL (People) cover?

People domain: common vision, conflict management, team leadership, stakeholder engagement, knowledge transfer, and communication - 33% of the July 2026 PMP exam. Learning outcomes: Develop a common vision; Manage conflicts; Lead the project team; Engage stakeholders; Align stakeholder expectations; Manage stakeholder expectations; Help ensure knowledge transfer; Plan and manage communication.

How is PMP-PPL assessed?

People is covered through PMP exam domain: the 180-question, 240-minute PMP exam; PMI does not publish a fixed passing percentage.