PRINCE2 Project Management Foundation (Version 7)

PRINCE2-F-LO3: Understand the importance of people in successful projects

The people element: project ecosystems, stakeholders, change management, leadership versus management, and building effective teams - 14% of the exam.

Objective response

What you will learn in PRINCE2-F-LO3

  • Understand the importance of people in successful projects

Free PRINCE2-F-LO3 study-note previews

Free PRINCE2-F-LO3 practice questions

A sample of 2 questions from the PRINCE2-F-LO3 question bank, with the answer and explanation for each. Try answering before you open the answer.

  1. Question 1

    What is a description of a purpose of the change management approach?

    • ATo describe how proposals to change the project baseline should be recorded and approved
    • BTo describe the standards required to deliver products that meet user's expectations
    • CTo define how the business will need to operate in the future to meet the project objectives
    • DTo describe the processes and procedures required to manage uncertainty
    Show answer and explanation

    Correct answer: C - To define how the business will need to operate in the future to meet the project objectives

    C - "To define how the business will need to operate in the future to meet the project objectives" is correct. The change management approach, part of the project initiation documentation, establishes the target organizational state the project needs in order to meet its objectives, and how the business will move from its current state, through any interim states, to that target. It focuses on organizational transition - how people and the business will work in future - rather than on controlling changes to project documents.

    Why the other options are wrong

    • A: Recording and approving proposals to change the project baseline is covered by the issue management approach, which explains how issues are captured and how baseline changes are assessed and controlled.
    • B: Describing the standards and techniques needed to deliver products that meet quality specifications is the purpose of the quality management approach, not the change management approach.
    • D: Describing the procedures, techniques and responsibilities for managing uncertainty is the purpose of the risk management approach, because risks are uncertain events that would affect objectives.
  2. Question 2

    Which activity should be managed carefully as part of 'leading across organizational boundaries', because it is likely to be performed by people outside the project team?

    • ASecuring funding from the business layer for the business case
    • BIntegrating new products into each impacted area of the business
    • CGaining commitment for the realization of benefits post-project
    • DDelivering the products to the agreed quality specifications
    Show answer and explanation

    Correct answer: B - Integrating new products into each impacted area of the business

    B - "Integrating new products into each impacted area of the business" is correct. Leading across organizational boundaries recognizes that many people who matter to a project are not in the project team. People within the business who are affected by the project, but do not work in it, may contribute by integrating the new products into their own area of the organization. Because the project manager has no direct authority over them, this work has to be led through influence and collaboration and managed with care.

    Why the other options are wrong

    • A: Securing funding is the responsibility of the project executive, who sits on the project board within the project management team. It is not work performed by people outside the project team.
    • C: The senior user, a project board member, is responsible for handover, adoption and continued benefits realization, including securing ongoing commitment from the user community. The accountable role is inside the project management team.
    • D: Delivering products to the agreed specifications is the team manager's responsibility, and the team manager is part of the project management team, not outside it.

Practise these interactively

Study PRINCE2-F-LO3 on Examova

Frequently asked questions

What does PRINCE2-F-LO3 (Understand the importance of people in successful projects) cover?

The people element: project ecosystems, stakeholders, change management, leadership versus management, and building effective teams - 14% of the exam. Learning outcomes: Understand the importance of people in successful projects.

How is PRINCE2-F-LO3 assessed?

Understand the importance of people in successful projects is covered through Objective response: a 60-question objective-response exam with a 70% pass mark.