PRINCE2-F-LO4: Understand the PRINCE2 Project Management practices and how they are applied throughout the project
The seven practices - business case, organization, plans, quality, risk, issues, and progress - the largest section, at 60% of the exam.
What you will learn in PRINCE2-F-LO4
- Understand the PRINCE2 Project Management practices and how they are applied throughout the project
Free PRINCE2-F-LO4 study-note previews
Free PRINCE2-F-LO4 practice questions
A sample of 7 questions from the PRINCE2-F-LO4 question bank, with the answer and explanation for each. Try answering before you open the answer.
Question 1
The business strategy has changed, requiring the scope of the project to be increased beyond the tolerances that have been agreed by the business layer. Which plan should be produced to include this change?
- AProject plan
- BStage plan
- CTeam plan
- DException plan
Show answer and explanation
Correct answer: D - Exception plan
D - "Exception plan" is correct. When a project or stage is forecast to exceed its agreed tolerances, the project manager raises an exception report. If the project board decides how to address the exception, an exception plan is prepared showing how the directed actions will be carried out; it replaces the plan it covers. Here the scope increase goes beyond the tolerances agreed with the business layer, so an exception plan is needed.
Why the other options are wrong
- A: The project plan is created in initiating a project and baselined on board approval. When tolerances will be exceeded, the response is an exception plan, not simply producing a project plan.
- B: A stage plan is prepared near the end of the current stage for the next stage. It is the normal planning route, not the response to a forecast breach of agreed tolerances.
- C: A team plan is produced by a team manager to carry out one or more work packages. It operates at delivery level and cannot address a scope change beyond tolerances set by the business layer.
Question 2
During a stage, the project manager recorded a new risk on the risk register. In which step of the business case management technique should its impact on the business case be assessed?
- ADevelop
- BCheck
- CMaintain
- DConfirm
Show answer and explanation
Correct answer: B - Check
B - "Check" is correct. The business case management technique has four steps: develop, check, maintain and confirm. In the check step, the business case is refined as costs, timescales, products and risks become better understood, and the project manager checks it when assessing progress, risks and issues to judge their impact on the business justification. A new risk recorded during a stage is therefore assessed against the business case in this step.
Why the other options are wrong
- A: The develop step is when the project mandate triggers starting up a project and is used to create the initial justification in the outline business case. It is not where a risk raised mid-stage is assessed.
- C: In the maintain step, the project manager updates the business case at the end of each stage with progress data and the latest forecasts. Assessing a newly raised risk's impact happens in the check step.
- D: The confirm step is when the business reviews whether the intended benefits have actually been realized, typically in post-project benefits reviews. It is not used for assessing risks during a stage.
Question 3
What is defined as having the authority to direct the project within the remit set by the business?
- AProject manager
- BProject executive
- CProject management team
- DProject board
Show answer and explanation
Correct answer: D - Project board
D - "Project board" is correct. In PRINCE2 7, the project board is accountable to the business for the success of the project and has the authority to direct the project within the remit set by the business. It represents the business, user and supplier interests and makes the key decisions, such as authorizing initiation, stages and closure, while delegating day-to-day management to the project manager within tolerances.
Why the other options are wrong
- A: The project manager has authority to run the project day to day on behalf of the project board, within agreed tolerances and constraints. Running is delegated management, not directing the project.
- B: The project executive is the single point of accountability for the project and chairs the board, but the definition of directing the project within the business's remit belongs to the project board as a body.
- C: The project management team is the whole structure: board, project manager, team managers, project assurance and project support. As a whole, it does not hold the authority to direct the project.
Question 4
What is a purpose of the risk practice?
- ATo address concerns about standards that are to be applied to products
- BTo identify the likelihood of a threat occurring and its possible impact on the project
- CTo guarantee delivery of the agreed scope on time, to cost and quality
- DTo ensure that problems are resolved before they have a chance to negatively impact the project
Show answer and explanation
Correct answer: B - To identify the likelihood of a threat occurring and its possible impact on the project
B - "To identify the likelihood of a threat occurring and its possible impact on the project" is correct. The purpose of the risk practice is to identify, assess and control uncertainties that would affect the project's objectives, improving its ability to succeed. A risk is measured by combining the likelihood of a threat or opportunity occurring with the size of its impact on objectives, so understanding a threat's likelihood and impact is central to the practice.
Why the other options are wrong
- A: Setting out the standards to be applied to products is covered by the quality management approach within the quality practice, not by the risk practice.
- C: Risk management improves the likelihood of success but cannot guarantee that scope, time, cost and quality objectives will be met. Uncertainty can be reduced and controlled, never removed entirely.
- D: A problem is an issue that has an immediate negative impact, so resolving problems belongs to the issues practice. The risk practice deals with uncertain events that have not yet happened.
Question 5
What is a purpose of the quality practice?
- ATo enable control by defining how the project will deliver the products to satisfy the business case
- BTo document the user requirements and ensure they remain unchanged throughout the project
- CTo identify how the project will ensure that the user requirements of the project's products are met
- DTo agree to deliver products that were not part of the project's business justification
Show answer and explanation
Correct answer: C - To identify how the project will ensure that the user requirements of the project's products are met
C - "To identify how the project will ensure that the user requirements of the project's products are met" is correct. The purpose of the quality practice is to document the user's requirements of the project's products and to establish the means by which they will be met. Quality in PRINCE2 is about making sure the products meet users' requirements and expectations so that the desired benefits can be realized, through quality planning, quality control and quality assurance.
Why the other options are wrong
- A: Enabling control by defining how products will be delivered to satisfy the business case is the purpose of the plans practice, which covers the what, who, how, where, when and how much.
- B: The quality practice documents requirements but does not freeze them. However carefully they are captured, the project management team should expect requirements to change and be ready to handle those changes.
- D: The quality practice's product-based focus actually helps avoid spending resources on work that cannot be traced back to the business justification. It does not approve out-of-justification products.
Question 6
An issue has been identified and its impact on the project scope needs to be understood. In which step of the issue management technique should the impact be understood?
- AAssessing issues
- BCapturing issues
- CDeciding on changes
- DImplementing changes
Show answer and explanation
Correct answer: A - Assessing issues
A - Assessing issues. In the issue management technique, once an issue has been captured it is assessed. Assessment asks two questions: does this issue affect the project and, if so, how? This is where the project management team works out the issue's impact on the project, including its effect on scope and on the other performance targets. Understanding that impact is what then allows a sensible decision to be made. A decision on the issue is only taken after this assessment, so understanding the impact on scope belongs in the assessing step.
Why the other options are wrong
- B: Capturing issues is about recording issues raised through any formal or informal communication channel. At this point the issue is logged, but its effect on the project has not yet been analysed.
- C: Deciding on changes covers the decision options for a request for change or off-specification, such as approving, rejecting, asking for an exception plan or requesting more information. It comes after assessment and relies on the impact already being understood.
- D: Implementing changes means recording approved changes in the project log and updating the affected management products and baselines. It happens after a decision has been made, well after the impact should have been understood.
Question 7
According to the exception management technique, at which levels are projects MOST LIKELY to identify issues that exceed stage tolerances?
- ACommissioning AND directing
- BDirecting AND managing
- CDirecting AND delivering
- DManaging AND delivering
Show answer and explanation
Correct answer: D - Managing AND delivering
D - Managing AND delivering. In exception management, the issues that threaten to take a stage outside its tolerances usually come up where the work happens. They are often met at the delivering level, where teams produce the products. They can also arise at the managing level, where the project manager deals with issues that are not caused by delivery problems. Once such an issue is identified, it is escalated to the directing level. There the project board decides whether to authorize a deviation beyond stage tolerances.
Why the other options are wrong
- A: The commissioning level, which is the business, sets project-level tolerances. The directing level, the project board, decides on deviations beyond stage tolerances. Neither level is where stage-threatening issues are usually identified.
- B: The managing level can identify such issues, but the directing level is where decisions about breaches of stage tolerance are made, not where the issues are usually encountered. The delivering level, where most of these issues arise, is left out.
- C: The delivering level is correct, but the directing level is where the project board makes decisions about deviations. It is not where issues that exceed stage tolerance are usually identified. The managing level is left out.
Study PRINCE2-F-LO4 on Examova
Frequently asked questions
What does PRINCE2-F-LO4 (Understand the PRINCE2 Project Management practices and how they are applied throughout the project) cover?
The seven practices - business case, organization, plans, quality, risk, issues, and progress - the largest section, at 60% of the exam. Learning outcomes: Understand the PRINCE2 Project Management practices and how they are applied throughout the project.
How is PRINCE2-F-LO4 assessed?
Understand the PRINCE2 Project Management practices and how they are applied throughout the project is covered through Objective response: a 60-question objective-response exam with a 70% pass mark.
All PRINCE2 Project Management Foundation (Version 7) modules