PRINCE2-F-LO5: Understand the PRINCE2 Project Management processes and how they are carried out throughout the project
The seven processes, from starting up a project through closing a project, and how each is carried out - 15% of the exam.
What you will learn in PRINCE2-F-LO5
- Understand the PRINCE2 Project Management processes and how they are carried out throughout the project
Free PRINCE2-F-LO5 study-note previews
Free PRINCE2-F-LO5 practice questions
A sample of 3 questions from the PRINCE2-F-LO5 question bank, with the answer and explanation for each. Try answering before you open the answer.
Question 1
Which is a purpose of the 'directing a project' process?
- ATo retain accountability of the project board while delegating the detailed management work
- BTo prevent any projects with poor justification from being undertaken by the organization
- CTo manage the work of a stage by implementing effective corrective actions
- DTo provide information so that the commissioning authority can commit to delivery of the project
Show answer and explanation
Correct answer: A - To retain accountability of the project board while delegating the detailed management work
A - To retain accountability of the project board while delegating the detailed management work. Directing a project enables the project board to be accountable for the project's success. The board does this by making key decisions and exercising overall control, while delegating day-to-day management of the project to the project manager. This reflects the directing level of PRINCE2's management structure: the board directs and does not manage the detail, but it remains answerable for the project.
Why the other options are wrong
- B: Preventing poorly justified projects from going ahead is the aim of starting up a project, which asks whether there is a viable and worthwhile project before initiation.
- C: Managing a stage's work and taking corrective action to keep the stage within tolerance is the purpose of controlling a stage. The project manager carries out this process, not the project board.
- D: Giving the business the information it needs to understand the work before committing significant resources is the purpose of initiating a project. That process produces the project initiation documentation.
Question 2
Which is a purpose of the 'starting up a project' process?
- ATo assess whether a project is likely to be valuable to the organization
- BTo analyze the work required before committing to implement the project initiation documentation
- CTo provide the opportunity for the users to confirm that they accept the project product
- DTo delegate the management of the project in a controlled way
Show answer and explanation
Correct answer: A - To assess whether a project is likely to be valuable to the organization
A - To assess whether a project is likely to be valuable to the organization. The purpose of starting up a project is to make sure the prerequisites for initiating a project are in place by answering one question: do we have a viable and worthwhile project? This is a short, light assessment before any commitment to initiation. It ensures time and money are not spent initiating a project that is unlikely to be valuable. The decision to start the project must be explicit, and the activities of starting up a project happen before that decision.
Why the other options are wrong
- B: Understanding the work needed before committing significant expenditure is the purpose of initiating a project. That process establishes solid foundations for the project and produces the project initiation documentation. It does not take place in starting up a project.
- C: Confirming acceptance of the project product is part of the purpose of closing a project. It provides a fixed point where acceptance is confirmed and the objectives are recognized as achieved.
- D: Delegating day-to-day management of the project in a controlled way is the purpose of directing a project. It lets the project board stay accountable while the project manager runs the project.
Question 3
Which TWO are objectives of the 'controlling a stage' process? 1. To ensure there are no uncontrolled changes to the products agreed by the project board 2. To ensure the project board is assured that all products in the stage plan have been completed 3. To ensure that the project initiation documentation is updated with any quality changes required for the next stage 4. To ensure that the products delivered during the stage meet the agreed quality criteria
- A1 and 2
- B2 and 3
- C3 and 4
- D1 and 4
Show answer and explanation
Correct answer: D - 1 and 4
D - 1 and 4. Controlling a stage is the process the project manager uses to assign and monitor work, deal with issues, report progress and take corrective action within stage tolerances. Its objectives include keeping attention on delivering the stage's products and monitoring any movement away from what was agreed, so that there are no uncontrolled changes (statement 1). They also include making sure the agreed products for the stage meet the agreed quality expectations and are accepted (statement 4). Together these keep the stage delivering the right products to the right quality.
Why the other options are wrong
- A: Statement 1 is correct, but statement 2 is not an objective of controlling a stage. Assuring the project board that everything is complete, with provision for anything still open, relates to closing activities, not the day-to-day control of a stage.
- B: Neither statement is an objective of controlling a stage. Statement 2 relates to closing activities. Statement 3 relates to initiating a project, where a common understanding of how the required quality will be achieved is established.
- C: Statement 4 is correct, but statement 3 is not. Setting out how quality will be achieved in the project initiation documentation is an objective of initiating a project, not of controlling a stage.
Study PRINCE2-F-LO5 on Examova
Frequently asked questions
What does PRINCE2-F-LO5 (Understand the PRINCE2 Project Management processes and how they are carried out throughout the project) cover?
The seven processes, from starting up a project through closing a project, and how each is carried out - 15% of the exam. Learning outcomes: Understand the PRINCE2 Project Management processes and how they are carried out throughout the project.
How is PRINCE2-F-LO5 assessed?
Understand the PRINCE2 Project Management processes and how they are carried out throughout the project is covered through Objective response: a 60-question objective-response exam with a 70% pass mark.