PRINCE2-F-LO1: Understand key concepts relating to projects and PRINCE2 Project Management
Key concepts: the five integrated elements, project and project-management definitions, performance aspects, and delivery approaches - 3% of the exam.
What you will learn in PRINCE2-F-LO1
- Understand key concepts relating to projects and PRINCE2 Project Management
Free PRINCE2-F-LO1 study-note previews
Free PRINCE2-F-LO1 practice questions
A sample of 1 question from the PRINCE2-F-LO1 question bank, with the answer and explanation for each. Try answering before you open the answer.
Question 1
Which is a characteristic of a project that distinguishes it from business as usual?
- AProjects continue after business as usual resumes
- BProjects include ongoing management of operations
- CEvery project will be different to previous projects
- DProject work is generally less risky than business as usual work
Show answer and explanation
Correct answer: C - Every project will be different to previous projects
C - "Every project will be different to previous projects" is correct. Uniqueness is one of the characteristics that distinguish projects from business as usual. Even when two projects look similar, something always differs: the team, the customer, the supplier, the location or the timeframe. These differences combine to make each project unique, which is why projects need their own management approach, planning and controls rather than relying purely on routine operational procedures. Other distinguishing characteristics include being temporary, introducing change, being cross-functional and carrying more uncertainty.
Why the other options are wrong
- A: Projects are temporary. Once the desired change has been implemented, business as usual resumes in its new form and the need for the project ends. Projects do not continue after business as usual resumes.
- B: Ongoing management of operations is business as usual itself, not a project. A project is a temporary organization set up to deliver change, after which the operational business takes over the products.
- D: The opposite is true. Because projects are unique, temporary and introduce change, they carry threats and opportunities beyond those normally met in business as usual. Projects are therefore riskier, not less risky.
Study PRINCE2-F-LO1 on Examova
Frequently asked questions
What does PRINCE2-F-LO1 (Understand key concepts relating to projects and PRINCE2 Project Management) cover?
Key concepts: the five integrated elements, project and project-management definitions, performance aspects, and delivery approaches - 3% of the exam. Learning outcomes: Understand key concepts relating to projects and PRINCE2 Project Management.
How is PRINCE2-F-LO1 assessed?
Understand key concepts relating to projects and PRINCE2 Project Management is covered through Objective response: a 60-question objective-response exam with a 70% pass mark.
All PRINCE2 Project Management Foundation (Version 7) modules