Projects and PRINCE2 7: key concepts

Free Preview

A project is a temporary organization created to deliver one or more business products according to an agreed business case, and it is characterized by change, being temporary, cross-functional, unique and uncertain. PRINCE2 manages seven aspects of project performance: benefits, cost, time, quality, scope, risk and sustainability. The method has five integrated elements: principles, people, practices, processes and the project context. Projects can use linear-sequential, iterative-incremental or hybrid delivery approaches, and PRINCE2 excludes detailed specialist techniques.

What is a project?

PRINCE2 defines a project as a temporary organization that is created for the purpose of delivering one or more business products according to an agreed business case. Two ideas sit inside that definition: a project is temporary (it is set up and then disbanded), and it exists to deliver products that are justified by a business case.

Project management is the application of methods, tools, techniques and competencies to a project. In practice it means planning, delegating, monitoring, controlling and motivating people so that the project delivers what was agreed.

Characteristics of a project

Five characteristics distinguish project work from business as usual:

  • Change – projects are the means by which an organization introduces change.
  • Temporary – when the desired change has been implemented, business as usual resumes (in its new form) and the need for the project is removed. A project does not carry on operating what it created.
  • Cross-functional – projects often work across the usual functional divisions within an organization and sometimes span different organizations. A question about teams from different organizations working together is testing this characteristic.
  • Unique – even when an organization runs many similar projects, each one differs in some way: a different team, customer, supplier, location or timeframe.
  • Uncertainty – the other characteristics introduce threats and opportunities beyond those normally met in business as usual, so projects are riskier than business as usual, not less risky.

Why project management is used

Because projects are temporary, cross-functional, unique and uncertain, normal line management arrangements are not enough to control them. Project management keeps the work under control across the aspects of performance below. PRINCE2 addresses these challenges with a common language, clear roles, a controlled lifecycle and a focus on products and business justification.

The seven aspects of project performance

PRINCE2 identifies seven aspects of project performance that must be managed:

  • Benefits
  • Cost
  • Time
  • Quality
  • Scope
  • Risk
  • Sustainability

Sustainability is a full performance aspect in PRINCE2 7, alongside the other six. These seven aspects are also the areas against which tolerances are set later in the method.

What PRINCE2 does not cover

PRINCE2 excludes detailed specialist techniques and specialist aspects of the work. It can be combined with whatever specialist techniques a project needs, but it does not prescribe them.

The five integrated elements

PRINCE2 is built from five integrated elements:

  1. Principles – guiding obligations that ensure effective application and tailoring of PRINCE2 to any project.
  2. People – those working on the project and those affected by it. Understanding their needs, capabilities, motivations and relationships is crucial to how the project is set up and run.
  3. Practices – aspects of project management that must be continually addressed throughout the lifecycle: business case, organizing, plans, quality, risk, issues and progress.
  4. Processes – seven processes describing the whole lifecycle, from activities before the project starts, through the stages of delivery, to final closure. Each process has recommended activities and related responsibilities.
  5. Project context – the setting in which the project runs. It influences how the principles, practices and processes are applied by the people involved, so that the method is fit for the project. Context factors include the project's scale, the organizational context, the commercial context, the delivery method and sustainability.

There are five elements, not four.

Users, suppliers and the business

Every PRINCE2 project has three interests:

  • a user, who specifies the desired outputs;
  • a supplier, who provides the resources and expertise to deliver the products;
  • the business, which provides the project mandate and the structure for project governance.

Projects also sit inside a wider organizational context, and may form part of a portfolio or a programme.

Delivery approaches

PRINCE2 recognizes three delivery approaches:

  • Linear-sequential – the delivery steps occur in sequence, and the product is made available during or at the end of the project. Example: a construction project where requirements gathering and design are completed before construction starts.
  • Iterative-incremental – the delivery steps (for example, requirements, design, development and testing) occur iteratively throughout the project. This is often referred to as an agile approach.
  • Hybrid – some elements of the project use a linear-sequential approach and others use an iterative-incremental approach, for example building infrastructure sequentially and then developing a customer portal iteratively.

Be careful not to confuse delivery approaches with controls: "event-driven" describes a type of control, not a delivery approach.

An overview of the PRINCE2 processes

The seven processes are starting up a project, directing a project, initiating a project, controlling a stage, managing product delivery, managing a stage boundary and closing a project. A few structural rules are worth knowing now:

  • Starting up a project happens pre-project and is used by both the directing and the managing levels.
  • A project has at least two stages, and the initiation stage always comes first.
  • The first use of managing a stage boundary comes as initiation ends, when the next stage is planned. It recurs at the close of every later stage apart from the final one, and it can also be used at any point to prepare an exception plan.

Features and benefits of PRINCE2

PRINCE2 is universal, flexible, proven and outcome focused. It provides a common language and concepts, supports increased organizational maturity, and is part of an integrated suite of methods.

Key Terms

projectA temporary organization created to deliver one or more business products according to an agreed business case.
project managementThe application of methods, tools, techniques and competencies to a project, including planning, delegating, monitoring, controlling and motivating.
five integrated elementsThe five building blocks of PRINCE2: principles, people, practices, processes and the project context.
principlesThe integrated element made up of the seven principles, each a guiding obligation that ensures effective application and tailoring of PRINCE2 to any project.
peopleThe integrated element covering those working on the project and those affected by it, including their needs, capabilities, motivations and relationships.
practicesThe integrated element made up of the seven aspects of project management that must be continually addressed throughout the lifecycle: business case, organizing, plans, quality, risk, issues and progress.
processesThe integrated element made up of the seven processes that describe the project lifecycle from pre-project activity to closure, with recommended activities and responsibilities.
project contextThe integrated element describing the setting of the project (for example scale, organizational and commercial context, delivery method, sustainability), which influences how the method is applied.
seven aspects of project performanceBenefits, cost, time, quality, scope, risk and sustainability: the aspects that must be managed and against which tolerances are set.
linear-sequentialA delivery approach in which delivery steps occur in sequence and the product is made available during or at the end of the project.
iterative-incrementalA delivery approach in which delivery steps occur iteratively throughout the project; often called an agile approach.
hybridA delivery approach in which some elements of the project are linear-sequential and others are iterative-incremental.
userThe project interest that specifies the desired outputs and will use them.
supplierThe project interest that provides the resources and expertise to deliver the products.
businessThe project interest that provides the project mandate and the structure for project governance.

Common Traps

  • PRINCE2 7 has five integrated elements, including people and project context. Do not answer with four elements or with older-edition 'themes'.
  • There are seven aspects of project performance. Sustainability sits alongside benefits, cost, time, quality, scope and risk; lists that leave it out are older-edition wording.
  • Projects are temporary: business as usual resumes when the change is implemented. Projects do not include ongoing operations, and they are riskier than business as usual, not less risky.
  • Teams from different organizations working together describes 'cross-functional', not 'unique' or 'temporary'.
  • Linear-sequential, iterative-incremental and hybrid are delivery approaches. 'Event-driven' is a type of control, not a delivery approach.
  • The project context influences how principles, practices and processes are applied. Do not confuse it with the practices (continually addressed aspects) or the processes (the lifecycle).
  • PRINCE2 excludes detailed specialist techniques. It is not a specialist engineering or development method.